The Dairy Road bridge over the U.S. 250 bypass closes fully on Jan. 4, 2027, for 12 to 14 months. Daytime lane closures on the bypass start the same day.
Overview
Updated Nov. 22: the project site now gives Monday, Jan. 4, 2027, as the start of the full closure of Dairy Road and of daytime lane closures on the U.S. 250 bypass below it.
The Dairy Road bridge over the U.S. 250 bypass will close completely on Monday, Jan. 4, 2027, while the city tears it down and builds a new one. The city expects the closure to last 12 to 14 months. The city presented the closure and detour plans at a community meeting Wednesday, Nov. 18.
The city said in a Nov. 10 notice that the bridge has reached the end of its useful life. A March 2025 inspection rated it in poor condition.
The closures from Jan. 4
The project website lists these construction updates:
- Dairy Road: full closure from Monday, Jan. 4, 2027
- U.S. 250 bypass, daytime: lane closures from Jan. 4, 9 a.m. to 3:30 p.m. Monday through Friday, as weather allows
- U.S. 250 bypass, overnight: full closures with all traffic detoured, 9 p.m. to 5 a.m. on weeknights, dates not yet set
- Dairy Road pedestrian bridge: open, with no closures scheduled
The city held its community meeting on the schedule, closure and detour on Nov. 18 at the Charlottesville Early Learning Center, 1564 Dairy Road.
Why the bridge is being replaced
The bridge was built in 1953, according to the project’s frequently asked questions page. Bridges of that era were designed to last about 50 years. The city says the bridge is still safe for cars and small trucks. Heavier loads are already restricted, and it is now inspected every 12 months.
The project is estimated to cost $12.62 million, including engineering and construction. It is paid for through VDOT’s State of Good Repair program, with state and federal money.
City Council heard an update on Dec. 15, 2025. The council voted unanimously to endorse the project, the project site says, while asking for ways to shorten the closure.
Why it has to close completely
The city looked at keeping one lane open with temporary signals. Its FAQ says drivers would have waited more than four minutes at each light. At busy times, the line would have backed up onto the bypass.
Building a new bridge beside the old one was also ruled out. A bridge to the west would cut into private property and mean rebuilding the bypass off-ramp. One to the east would remove the pedestrian bridge the city finished in 2017 and could affect a Dominion transmission tower.
That pedestrian bridge stays open during the work, the project’s about page says. It will close only for short periods when construction makes that necessary.
The schedule so far
The estimated schedule on the project site lists these dates:
| Milestone | Estimated date |
|---|---|
| Construction begins | December 2026 |
| Bridge closes | February 2027 |
| New bridge reopens | March 2028 |
| Construction complete | May 2028 |
The project site now puts the full closure at Jan. 4, 2027, about a month earlier than the table shows. The reopening and completion dates have not been updated. The city calls every future date an estimate.
The detour
The city has drawn up official detour routes that will be signed for the whole closure. Its July 2025 hearing brochure lists two changes along them:
- a temporary traffic signal where the U.S. 250 bypass eastbound off-ramp meets Rugby Avenue
- new signal timings along the detour routes while the bridge is closed
The routes themselves are on the detour maps. The city says it will watch traffic on the detour and add other fixes if needed.
What the new bridge will look like
After the July 2025 public hearing, the city agreed to make the new bridge look more like the Route 250 bridge over McIntire, the project site says. The plans add painted girders, a decorative steel railing in place of a plain concrete barrier and a stone finish on the foundation walls.
What it means for you
- If you cross the bypass on Dairy Road, plan on a signed detour for about a year starting Monday, Jan. 4, 2027.
- If you drive the U.S. 250 bypass by Dairy Road on weekdays, expect lane closures from 9 a.m. to 3:30 p.m. from the same day, and watch the project site for overnight full closures.
- Walkers and cyclists keep the pedestrian bridge for most of the work.
- Questions can go to the city through the project contact page.